“We are waiting for the customer” explains a position. It does not yet explain the promise, the supplier’s own next step or the price of the wait.

Put the dependency beside the delivery commitment before turning the sentence into an invoice or an accusation.

The promise has more than one moving part

This constructed service arrangement supplies the following terms for a draft asset report:

The customer supplies the complete asset list before analysis begins. The supplier provides a list template in advance, checks the submission within one working day and identifies any missing required fields. The supplier delivers the draft report five working days after confirming in writing that the list is complete.

For this illustration, working days are counted in a simple sequence. The initial plan places receipt on day 0, completeness confirmation on day 1 and draft delivery on day 6. No separate fixed delivery date, delay-payment term or liability rule is supplied.

That last sentence matters. The example gives us a dependency and a way to count a delivery interval. It does not give us a price for delay.

Supplier reading: the input starts the analysis clock

If the list arrives on day 2, is complete and is confirmed on day 3, the five-working-day draft interval would end on day 8 in this sequence. The difference from the initial plan is two working days.

The supplier can make that dependency visible. It cannot use the dependency to erase the obligations to supply the template, examine the submission promptly and identify missing fields. “Waiting” is an incomplete account if a list has arrived and nobody has checked it.

A proposed status message might say:

The list arrived on day 2. We will complete the agreed completeness check within one working day. If we confirm it complete on day 3, the draft interval runs to day 8 under the supplied sequence. We will identify any missing required fields in the check response. Please also flag any separate delivery commitment we need to consider before agreeing the revised plan.

This communicates a conditional sequence. It does not pretend that a check has already happened.

Customer reading: a dependency is not an unlimited pause

The customer can reasonably ask which required information is missing, when the supplier will check it and what work can proceed in the meantime. Those questions help distinguish an input problem from an unclear process or an avoidable wait.

The customer should also be able to see the assumptions used in the revised plan. If the supplier has silently added a new validation requirement, the original dependency clause does not explain that change. The parties need to identify it and decide how it fits the work.

The useful record connects the requested input, its receipt, the check result, the completeness confirmation and the delivery interval. It keeps each party’s part visible.

Discuss cost as another question

Replanning may raise a genuine commercial question about reserved capacity, extra checking or changed work. Identify the proposed cost and its basis separately. The fact that an input arrived later than planned does not itself supply every missing term about additional payment, liability or an enforceable extension.

For a real engagement, examine the whole agreement and relevant circumstances before drawing those conclusions. The arithmetic above establishes a conditional working sequence, not a legal remedy.

First identify which promise depends on which input. Then decide what needs changing, who may agree it and how the resulting arrangement will be recorded. A delay is expensive enough without charging it for questions the record has not answered.